For this assignment, you will utilize Microsoft Visio® to complete this activity. Before you begin to work on this activity, review the tutorials presented on the Microsoft Project and Microsoft Visio page. Given the following activities and precedents, draw a PERT/CPM diagram. ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A – 10 B – 12 C A 4 D A, B 8 E A, B 9 F C 10 G D, F 12 H E, G 15 Answer the following: What is the critical path? How long will it take to complete this project? Can activity E be delayed without delaying the completion of the project? If so, how many days? https://e5.onthehub.com/WebStore/Account/AcceptTermsOfService.aspx?ws=36cd252d-2829-e811-8101-000d3af41938&vsro=8 https://trainme.erau.edu/acadtech/Integration-Instructions/download-install-visio-project/index.html